What it is for
Every farm reaches the same wall: the containers arrive faster than the transformer. A substation skid ordered with the first container is what keeps a site on schedule.
We build the transformer, the MV switchgear and the LV distribution on one ISO skid, wired and tested, so the site work is a cable trench and a fence rather than a switchgear room.
Where it is typically used
Key specifications
| Rating | 1.25 or 2.5 MVA, ONAN |
| MV | 10 or 35 kV, ring main unit, 3 or 4 way |
| LV | 400/415 V, 4–8 outgoing feeders |
| Protection | Overcurrent, earth fault, Buchholz, temperature |
| Parallel | Up to 4 skids on one bus with load sharing |
| Skid | ISO corner castings, lifting lugs, bunded floor |
| Footprint | 6,058 × 2,438 mm, 20 ft envelope |
| Build time | 45–60 days, transformer lead time excluded |
Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.
What goes in the box
Installed, wired and tested before dispatch. On site the work is placement and external connections.
Oil-immersed ONAN unit with tap changer and temperature protection.
Ring main unit with earthing switch and interlocks.
Outgoing feeders to each container, metered per feeder.
Bunded steel frame with ISO castings, liftable by reach stacker.
Relays, CTs and a test terminal block a third party can verify.
Which model to take
| Model | Rating | MV | Feeders | Containers |
|---|---|---|---|---|
| MC-SUB-12 | 1.25 MVA | 10 kV | 4 | 6–8 |
| MC-SUB-25 | 2.5 MVA | 10 kV | 8 | 12–16 |
| MC-SUB-25H | 2.5 MVA | 35 kV | 8 | 12–16 |
Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.
Order the transformer first, the containers second
MV equipment is the long pole
A container is 30–45 days. A 2.5 MVA transformer with a ring main unit has run 30–50 weeks on some routes. If the two are ordered together, the site waits for the transformer either way — so order it first and let the containers catch up.
The one thing not to do is size the skid for the first stage. A 1.25 MVA unit bought for six boxes will not carry twelve, and a second skid costs more than the difference.
When to use it, when not to
These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.
The skid is cheaper than a switchgear room and arrives assembled.
Everything lifts out with the containers.
Then you need LV distribution, not a substation.
Some do. We will still supply the switchgear, but not the walls.
From contract to energisation
MV voltage, fault level, container count, utility requirements.
Single-line diagram and protection schedule in 7 days.
45–60 days after the transformer lands.
Two days to set and terminate, one day to commission.
On site and in detail




Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.
What customers ask most
Can you supply the transformer locally?
We can specify it and you buy locally to avoid freight and duty. The skid is built around a known envelope.
What fault level do you design for?
25 kA for three seconds as standard, higher on request.
Is the skid certified?
The frame is built to ISO 1496 lifting practice; the electrical assembly is tested to IEC 61439.
Ask for a scheme for your site
Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.