20GP Water-Cooled Mining Container — 96 Hydro Units at 0.55 MW

20GP Water-Cooled Mining Container — 96 Hydro Units at 0.55 MW

Categories:

96 S21 hydro units at 0.55 MW in a 20 ft container, two units per 40HQ, with a 60 m³/h glycol loop.

96S21 hydro
0.55 MWdesign load
2per 40HQ
60 m³/hloop flow
01 / OVERVIEW

What it is for

A 20 ft water-cooled box is what you buy when the site is small, the power is cheap and air cooling would need a box twice the size. Ninety-six hydro units on two racks, a 60 m³/h loop and a CDU that fits behind the door.

It is also the box for a site where the trailer cannot be longer than six metres: the loop and the machine count scale down together, so nothing here is a compromise on the cooling principle, only on the volume.

Where it is typically used

Small hydro sitesUnder 1 MW, where a 40 ft box would be under-filled.
Container campsWhere the dry cooler is shared between two or three boxes.
Indoor hallsFits through a standard roller door and into a bay.
Noise-limited yardsQuieter than air cooling at the same load.
02 / SPECIFICATIONS

Key specifications

Shell 20GP, CSC plated, 6,058 × 2,438 × 2,591 mm
Units 96 × S21 hydro, 2 racks × 4 layers × 12
Design load 0.55 MW
Loop 40% glycol, 60 m³/h, DN32 304 stainless
CDU Single pump, plate heat exchanger, 600 kW rejection
Power 1 × 800 A main, 48 × 20 A branch
Noise 55 dB(A) at 10 m
Build time 30–40 days from drawing release

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Shell and racks

Certified 20GP with two four-layer hydro racks and manifold at the rear.

02CDU

Pump, plate exchanger, strainer and bypass, accessible from the door.

03Manifold

Twelve outlets per rack side, drip tray under each layer.

04Control

Loop temperature and differential pressure to your SCADA, dry contacts.

05Spares

Pump seal, hose set, one manifold outlet and a glycol test kit.

04 / MODELS

Which model to take

Model Units Load Loop Cooler
MC-WAT-20-S 96 0.55 MW 60 m³/h 1 × 600 kW
MC-WAT-20-L 84 0.48 MW 60 m³/h 1 × 500 kW
MC-WAT-20-P 96 0.55 MW 60 m³/h Shared 1.3 MW bank

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Sharing one dry cooler between boxes saves more than it costs

ENGINEERING NOTE

A shared bank is normal practice below 2 MW

Two 20 ft boxes and one 1.3 MW dry cooler cost less than two dedicated coolers, occupy less pad, and give you N+1 on the fans. The price is that the loop has to be balanced and the PLC has to know which box is which.

We size shared banks at 1.1× the sum of the boxes rather than 1.3× each, because they rarely peak together and the diversity is real.

Loop balancing valves are set at commissioning and tagged; a shared bank without them will starve the furthest box.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

You want hydro density on a site that cannot take a 40 ft.

This is the only configuration that fits.

You will add a second box within a year.

Buy the shared cooler now; retrofitting a bank costs more than upsizing it.

You have no one to maintain glycol.

A water loop needs a quarterly check. Without it, air is honest.

Your ambient drops below −30 °C.

At 40% glycol the loop gels. Go to 50% and tell us the winter minimum.

07 / DELIVERY

From contract to energisation

Drawing

Unit model, ambient range, cooler location. Five days.

Production

30–40 days, loop pressure-tested before shipping.

Test

Loop at 1.5× working pressure, then 24 hours on load.

Ship

Two per 40HQ; manifolds braced, glycol shipped separately.

08 / GALLERY

On site and in detail

A 20 ft water-cooled container on site
A 20 ft water-cooled container on site
Service aisle between the hydro racks
Service aisle between the hydro racks
Shell before the manifolds are fitted
Shell before the manifolds are fitted
Electrical cabinet with the loop controls
Electrical cabinet with the loop controls

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Can the cooler be on the roof of the box?

At 600 kW, yes on some builds, but the structure needs reinforcing and access for cleaning is poor. Grade level is better.

How much glycol per box?

About 0.9 m³ including the loop to the cooler.

Does it need a water supply?

No. It is a closed glycol loop with a dry cooler; water is only needed for the initial fill.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the mining range

Product Details
gallery
RELATED PRODUCT
Electrical distribution cabinet inside a mining container
Mining PDU & Monitoring — Per-Position Metering and Remote Power Cycling
A dry cooler heat rejection skid with axial fans
Heat Rejection Skid — 300 to 1,500 kW of Dry Cooling
An immersion-cooled mining container with tanks of dielectric fluid
40HC Immersion Mining Container — Up to 1.4 MW in Dielectric Fluid
Row of air-cooled mining containers deployed as a farm
Air-Cooled Mining Farm — 2 to 10 MW in 40 ft Containers
Contact us

Committed to providing customers with high-quality and reliable container solutions.