40HC Water-Cooled Mining Container — 210 S21 Hydro Units at 1.2 MW

40HC Water-Cooled Mining Container — 210 S21 Hydro Units at 1.2 MW

Categories:

210 S21 hydro units at 1.2 MW in one 40 ft shell — heat leaves through a pipe instead of a fan.

210S21 hydro
1.2 MWdesign load
57 dB(A)at 10 m
1,306 kWdry cooler
01 / OVERVIEW

What it is for

This is the density play. Same 40 ft shell as the air-cooled box, seven times the compute, because the heat leaves through a pipe instead of a fan. Two racks of seven layers, fifteen units per layer, a 150 m³/h glycol loop and a dry cooler outside.

It is not a cheaper box — it is a smaller site. At 1.2 MW per container, a 10 MW farm needs nine boxes instead of fifty-six, and the fencing, the cabling and the land all shrink with it.

Where it is typically used

Dense farmsWhere land or pad area is the constraint, not the machines.
Noise-controlled sites57 dB(A) at ten metres is a fence-line number, not a plant-room number.
Hot climatesThe loop does not care about 45 °C ambient if the cooler is sized for it.
Cheap power, expensive landThe economics invert in favour of water.
02 / SPECIFICATIONS

Key specifications

Shell 40HC, CSC plated, 12,192 × 2,438 × 2,896 mm
Units 210 × S21 hydro, 2 racks × 7 layers × 15
Design load 1.2 MW at 35 °C ambient
Loop 40% glycol, 150 m³/h, DN57 304 stainless
CDU Single pump, 150 m³/h, plate exchanger
Heat rejection Dry cooler 1,306.8 kW, 1,741 m² coil, 8 × 910 mm fans
Fan power 33.2 kW total, 240,000 m³/h
Noise 57 dB(A) at 10 m
Power 2 × 1,250 A, 105 × 20 A per cabinet
Build time 35–50 days from drawing release

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Shell and racks

Two seven-layer hydro racks with 28-way manifold, fifteen outlets per side.

02CDU

150 m³/h pump, plate exchanger, strainer, bypass and fill point.

03Loop pipework

DN57 304 stainless, insulated, pressure-tested at 1.5× before shipping.

04Dry cooler

Shipped with the box; site piping and the pad are site work.

05Control and spares

PLC interlinking CDU and cooler fans; pump seal, hoses, glycol kit.

04 / MODELS

Which model to take

Model Units Load Cooler Ambient
MC-WAT-40-S 210 1.2 MW 1,306 kW 35 °C
MC-WAT-40-H 210 1.2 MW 1,500 kW 45 °C
MC-WAT-40-C 196 1.12 MW 1,306 kW −30 °C

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

The 8.9% margin on the dry cooler is the whole design

ENGINEERING NOTE

Sizing at the load is how loops derate

The cooler is rated 1,306.8 kW against a 1,200 kW design load. That 8.9% covers a dirty coil, a hot week and a glycol mix that is richer than ideal. Size it at 1,200 kW and the loop runs at 45 °C instead of 40, the machines throttle, and the farm makes less than its nameplate for the hottest six weeks of the year.

The trade is fan power: eight 910 mm fans moving 240,000 m³/h cost 33.2 kW, which is 2.8% of the load. That is the cheapest insurance in the box.

Cooler sizing is issued with wet-bulb, altitude and glycol concentration written on it, so the margin can be audited.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

You need more than 400 kW on a pad that will not grow.

Water is the only route at this density.

You have somewhere to put a dry cooler.

Plan the pad, the pipe run and the cleaning access before you order.

You cannot maintain a glycol loop.

A pump seal and a quarterly test are not optional, and a failed loop cooks 210 machines.

The site is remote from any fluid delivery.

Several tonnes of glycol have to reach the site once, and again after any major repair.

07 / DELIVERY

From contract to energisation

Drawing

Unit model, ambient, wet-bulb, altitude, cooler position. 7 days.

Production

35–50 days, loop tested before dispatch.

Test

Pressure test at 1.5×, then 72 hours at design load with the ambient logged.

Ship

Container and cooler on one bill; site piping by others.

08 / GALLERY

On site and in detail

A 40 ft water-cooled container outdoors at dusk
A 40 ft water-cooled container outdoors at dusk
Hydro racks with the manifold at the rear
Hydro racks with the manifold at the rear
Shell internals before the loop is fitted
Shell internals before the loop is fitted
Container row with the cooler bank set back
Container row with the cooler bank set back

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Can I use my own dry cooler?

Yes, if it is rated for the flow and the approach. Send the curve; we will check it against the loop before we ship.

What if the pump fails?

The PLC drops the load on the affected rack and alarms. A standby pump is an option and is worth taking on unmanned sites.

How long does commissioning take?

Three to four days: flush, fill, leak test, then a 72-hour run at design load.

Is 1.2 MW achievable at 45 °C ambient?

Yes, with the larger cooler. The box does not change; the rejection side does.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the mining range

Product Details

Seven times the compute in the same footprint

Two racks of seven layers, fifteen units per layer, 210 machines in total. Heat goes into a closed loop
of 40 % ethylene glycol driven by a single-pump CDU at 150 m³/h, through 304 stainless DN57 pipe and
a 28-way manifold with fifteen outlets each.

The part that lives outside the box

Rejection happens at a dry cooler rated 1,306.8 kW against a 1,200 kW design load — an 8.9 % margin,
1,741 m² of coil, eight 910 mm fans moving 240,000 m³/h for 33.2 kW, at 57 dB(A) at ten metres.
That margin is not generosity; it is what stops the loop derating in the hottest week of the year. You need
room for the cooler, glycol top-up on site and a PLC that interlinks CDU and fans.

Key figures

  • 210 × Antminer S21 hydro · 1.2 MW design load · 40HC shell
  • 2 racks × 7 layers × 15 units · front and rear service access
  • Closed loop, 40 % ethylene glycol · single-pump CDU 150 m³/h
  • 304 stainless DN57 pipe · 28-way manifold, 15 outlets per way
  • Dry cooler 1,306.8 kW @ 1,200 kW · 1,741 m² coil · 57 dB(A) @ 10 m
  • PLC interlock between CDU, fans and leak detection

Built to order. Water chemistry, glycol concentration and cooler position are set per
site — send the ambient and the water analysis and we quote the loop around them.

gallery
RELATED PRODUCT
A dry cooler heat rejection skid with axial fans
Heat Rejection Skid — 300 to 1,500 kW of Dry Cooling
A containerised transformer and switchgear skid outdoors
Mining Substation & Paralleling Skid — 1.25 to 2.5 MVA
A 20-foot water-cooled mining container on a paved site
20GP Water-Cooled Mining Container — 96 Hydro Units at 0.55 MW
Row of air-cooled mining containers deployed as a farm
Air-Cooled Mining Farm — 2 to 10 MW in 40 ft Containers
Contact us

Committed to providing customers with high-quality and reliable container solutions.