Skid Base & Lifting Frame — ISO Corners, Lifting Lugs, Sea-Fastened

Skid Base & Lifting Frame — ISO Corners, Lifting Lugs, Sea-Fastened

Categories:

ISO skid bases and lifting frames rated 4–40 t, with certified lugs, a stated tie-down pattern and the sea-fastening load case on the drawing.

ISOcorner castings
4–40 trated load
2 gsea fastening
15 daysbuild
01 / OVERVIEW

What it is for

A skid is the difference between equipment that ships as freight and equipment that ships as a problem. It has to carry the load, be liftable by a reach stacker, survive a sea crossing, and be something a surveyor will sign off.

We build skid bases and lifting frames with ISO corner castings, certified lifting lugs and a stated load rating, designed for the transport configuration that will actually be used — including the tie-down points for sea fastening.

The common failure is a frame designed only for static load. A container in a seaway sees accelerations a static calculation never considers, and a skid that was “strong enough” arrives with a bent frame and an insurance claim.

Where it is typically used

Equipment that is not a containerTransformers, gensets, process skids and tanks that need an ISO envelope to travel.
Roof and deck mountingA frame that spreads the load and gives you lifting points.
Rented or relocated plantLift it, move it, set it down — no foundation to break out.
Sea freight of heavy itemsA frame that satisfies the surveyor and the stowage plan.
02 / SPECIFICATIONS

Key specifications

Rating 4–40 t static, stated with the calculation
Frame Welded steel, blasted and coated; galvanised on request
Corners ISO 1161 corner castings, four or eight depending on the frame
Lifting Certified lugs or corner-casting lift, with the centre of gravity marked
Sea fastening Tie-down points at a stated pattern, designed for 2 g longitudinal
Deck Open frame, chequer plate or timber deck
Bunding Optional drip tray or full bund, sealed and drained
Envelope 10, 20 or 40 ft ISO, or a custom footprint
Coating C4 standard, C5-M on request
Documentation Load calculation, lifting certificate and coating report
Build time 10–20 days depending on the frame

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Frame

Welded steel designed for the load case and the transport case, not just the static one.

02ISO corners

Cast or fabricated corner castings to ISO 1161, so any handler can lift it.

03Lifting points

Lugs or corner lift, certified, with the sling angles stated.

04Tie-downs

A stated pattern of points for sea fastening, with the design acceleration on the drawing.

05Deck and bund

Chequer plate, timber or open, with an optional sealed drip tray.

06Documentation

Load calculation and lifting certificate issued with the unit.

04 / MODELS

Which model to take

Model Envelope Rating Deck Use
EQ-SKID-10 10 ft ISO 8 t Open or plate Small skid or pump set
EQ-SKID-20 20 ft ISO 20 t Plate Transformer, genset
EQ-SKID-40 40 ft ISO 40 t Plate Process skid, tank
EQ-SKID-C Custom footprint To calculation To spec Oversize or odd shapes

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Design for the sea crossing, not for the yard

ENGINEERING NOTE

Static load is half the calculation

A container in a seaway is designed for accelerations in the order of 2 g longitudinally and 1 g vertically, depending on the stow position and the route. A frame designed only for its own weight will deform under that, and the deformation does not come out.

So the tie-down pattern and the accelerations go on the drawing, and the frame is checked against them rather than against a stack of assumptions.

The lift is where people get hurt

Lifting lugs are only as good as their certification and the sling angle assumed in the design. We state the angle, mark the centre of gravity and issue the certificate, because the lift happens once and there is no second chance.

Corner castings are the other route: any handler in the world can lift an ISO frame, and no rigger has to guess.

The transport load case and the tie-down pattern are stated on the drawing. If the route changes, the calculation is re-run before the frame is welded.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

Your equipment is not a container but must travel like one.

That is what an ISO skid is for.

The plant will be relocated.

No foundation to break out.

A surveyor has to sign the stowage.

We issue the load case and the tie-down pattern.

The equipment can sit on a simple concrete plinth.

A skid adds cost without adding value.

You need a wheeled trailer.

That is the trailer-mounted product, not a static skid.

07 / DELIVERY

From contract to energisation

Data

Equipment weight and centre of gravity, envelope, lifting method, transport route.

Design

Frame calculation and drawing in 5–7 days.

Contract

Drawing release and deposit; steel ordered.

Production

10–20 days: cut, weld, blast, coat, certify.

Handover

Load calculation, lifting certificate, coating report and markings.

08 / GALLERY

On site and in detail

An equipment frame with access ladders and lifting points
An equipment frame with access ladders and lifting points
Skid-mounted equipment standing outdoors
Skid-mounted equipment standing outdoors
ISO frame base prepared for equipment mounting
ISO frame base prepared for equipment mounting
Units staged on frames before loading
Units staged on frames before loading

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Do you provide a lifting certificate?

Yes, with the load case and the sling angles stated. It is issued with the frame, not afterwards.

Can the skid be galvanised?

Yes, hot-dip galvanised after fabrication. It is the right choice for coastal and offshore sites.

What if our equipment changes weight?

Tell us before the frame is welded. After welding the calculation is a rework, and we will quote it as one.

Is a bund available?

Yes, a sealed drip tray or a full bund with a drain valve. For oil-filled equipment it is usually a requirement, not an option.

Can it stack?

Only if designed for it, and stacking is a different load case. Say so at enquiry, not after delivery.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the enclosure range

Product Details
gallery
RELATED PRODUCT
Card Eq Hvac V2
Enclosure HVAC & Ventilation — Cooling, Explosion-Proof Fans, Motorised Louvres
Card Eq Pump
Pump & Compressor House — Heavy Floor, Acoustic Lining, Real Ventilation
Card Eq Lab V2
Mobile Laboratory Container — Fume Extraction, Bench and a Sink That Drains
Water treatment container with access doors (catalogue crop)
Water Treatment Container — Filtration, Dosing and Pump Sets Pipeless on Site
Contact us

Committed to providing customers with high-quality and reliable container solutions.