Battery Energy Storage Container — 10, 20 and 40 ft with Fire and Thermal

Battery Energy Storage Container — 10, 20 and 40 ft with Fire and Thermal

Categories:

Battery storage containers in 10, 20 and 40 ft: 5 kW to 25 kW of cooling, C4 coating, clean-agent fire kit, 35-day typical build.

10–40 ftshell
5 kWcooling in a 10 ft
C4corrosion
35 daystypical build
01 / OVERVIEW

What it is for

A battery container is not a box with a door. It is a thermal enclosure, a fire compartment and an electrical room wrapped around equipment somebody else warrants — and the boundary between your supplier’s responsibility and ours is exactly where projects go wrong.

We build the room: shell, insulation, thermal management, fire detection and suppression, DC and AC cable entries, lighting, earthing and the environmental monitoring that tells you the room is drifting before the battery does. The racks, the PCS and the transformer are yours or sourced as a named make.

The number that decides everything is the heat loss figure in kW, not the nameplate capacity in MWh. Give us the loss figure and the design ambient and the cooling is arithmetic. Give us a megawatt-hour number and we are guessing — which is how containers end up derated in their first August.

Where it is typically used

Utility-scale BESS20 or 40 ft shells holding racks plus PCS, on a pad with a transformer alongside.
Commercial peak shavingA 10 ft unit at 5 kW cooling behind a factory, small enough to fit an existing yard.
Solar and wind co-locationDC-coupled containers at the array, sized for the ambient on that site rather than a catalogue.
Microgrid and island sitesContainerised storage where the alternative is a masonry building nobody can ship.
02 / SPECIFICATIONS

Key specifications

Shell 10 ft / 20 ft / 40 ft HC, CSC plate, 50 mm insulated roof
Thermal management 5 kW split unit in a 10 ft; 10–25 kW in 20/40 ft, or liquid cooling on request
Insulation Polyurethane sandwich panel, 50–100 mm walls, thermal break at the frame
Fire detection Aspirating or point smoke, linear heat cable, gas detection where required
Fire suppression Clean agent (NH-200 / FK-5-1-12) or aerosol, cylinders reachable for weighing
Ingress IP54 standard, IP55 on request; louvred or ducted ventilation
Corrosion C4 three-coat epoxy as standard, C5-M for coastal and offshore
Floor loading Designed to the rack weight you state, 500–1,500 kg/m² typical
Cable entry Split gland plates, spare ways capped, DC and AC segregated
Electrical Lighting, sockets, earthing boss at each corner, DC distribution on request
Monitoring Temperature, humidity, door, smoke and water ingress to your SCADA by dry contact or Modbus
Design ambient −40 °C to +55 °C, stated in the contract

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Shell and paint

Certified container or new-build frame, blasted and coated to the agreed corrosion class.

02Insulation and lining

PU or rock wool to the thermal requirement, vapour barrier, sealed floor, wipe-clean lining.

03HVAC

Split or ducted cooling sized to your loss figure at your design ambient, with redundancy on request.

04Fire package

Detection loop, agent cylinders, alarm panel and a relay that cuts the PCS before the agent discharges.

05Electrical

Distribution, lighting, sockets, earthing; factory-tested and labelled before shipment.

06Documentation

As-built drawing, test sheet, nameplate, spare list and O&M file travel with the unit.

04 / MODELS

Which model to take

Model Shell Cooling Fire Typical use
EQ-BESS-10 10 ft · 2,991 × 2,438 5 kW split Clean agent + detection Small C&I, tight yards
EQ-BESS-20 20 ft · 6,058 × 2,438 10–15 kW Clean agent + detection Racks plus PCS
EQ-BESS-40 40 ft · 12,192 × 2,438 15–25 kW Clean agent + detection Utility block, multi-rack
EQ-BESS-40L 40 ft · liquid cooled CDU + dry cooler Detection + interlock High-density, hot climates

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Size the cooling from the loss figure, never from the megawatt-hour rating

ENGINEERING NOTE

Nameplate capacity tells you nothing about heat

A 2 MWh rack and a 5 MWh rack can dissipate the same kW, or ten times as much, depending on chemistry, C-rate and the efficiency curve of the PCS. Quoting cooling from the energy rating is the single most common way a battery container gets undersized.

So we ask for the loss figure per rack at your duty cycle, and we write the design ambient beside it on the drawing. If the number turns out to be wrong later, at least the assumption is documented and the fix is a known quantity.

Fire strategy follows the chemistry, not the brochure

Lithium fires do not behave like diesel or paper fires. The agent, the detection logic and the ventilation strategy all change with cell chemistry, and some insurers require a specific standard rather than any clean agent.

We build to the standard your insurer or your market requires — European-style kits for the EU, NFPA arrangements for North America — and we do not claim a certification for the box alone. The certificate stays with the equipment and its integrator.

The heat loss in kW, the design ambient and the fire standard your insurer requires are written on the general arrangement drawing before production starts.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

You have the rack layout and the heat loss in kW.

That is everything we need to size the room properly.

The site has no room for a masonry building.

A container is lifted onto a pad in a day and can move later.

You want one supplier for the room and your own OEM for the battery.

You keep your supplier’s warranty; we warrant the envelope around it.

You only have a megawatt-hour figure and no rack drawing.

We will quote a range, but the number will move once the real loss figure arrives.

Your utility requires a fire-rated masonry enclosure.

Some do. We will supply the equipment and the layout, not the walls.

07 / DELIVERY

From contract to energisation

Data

Rack drawing, heat loss in kW, design ambient, fire standard, voltage and cable schedule.

Drawing

General arrangement, cooling calculation and single-line in 5–7 working days.

Contract

Drawing release and deposit; long-lead items ordered first.

Production

30–45 days; 35 typical. Coating, lining, penetrations, HVAC, electrical, factory test.

Handover

Photographs at each hold point, as-built drawing, test sheet and O&M file with the unit.

08 / GALLERY

On site and in detail

Battery storage containers on a customer pad, cabled and commissioned
Battery storage containers on a customer pad, cabled and commissioned
PCS and storage units standing in a row outdoors
PCS and storage units standing in a row outdoors
Container ends with cooling and cable entries
Container ends with cooling and cable entries
Equipment containers staged on a site before connection
Equipment containers staged on a site before connection

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Can you supply the battery and the PCS too?

We can source them as a named make with a model number, so you can compare against your own supplier. Our margin is on the room, not on hiding the equipment price.

What cooling do I need for a 40 ft unit?

Between 15 and 25 kW for most rack layouts, but it follows the loss figure rather than the shell size. Send the rack datasheet and we will size it.

Is one unit a real order?

Yes. These are not stock items, so a single unit is built to your drawing with the same hold points as a batch of twenty. Only the unit price changes.

What about the foundation and the transformer?

We provide the load plan and lifting points. The plinth, anchor bolts, earthing grid and transformer are site work or quoted separately.

Can we inspect during the build?

Three hold points are open to you: after coating, after lining and penetrations, and before the factory electrical test. Come to Shenzhen or join by video.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the enclosure range

Product Details

The battery is yours. The room around it is the part that passes inspection.

A BESS enclosure is a thermal problem, a fire problem and a corrosion problem in that order. We build
the shell around the racks you have chosen: insulated to the ambient on your site, partitioned to the fire
strategy your insurer accepts, and finished to C4 as standard rather than as an upgrade.

Where these sit

Behind a solar farm, beside a substation, on a factory yard doing peak shaving. In every case the
enclosure has to hold its internal temperature through the afternoon peak and keep a fire inside one
compartment — which is why the louvre schedule and the partition detail matter more than the paint.

Key figures

  • 20 ft and 40 ft shells · custom skids on request
  • C4 corrosion class as standard · three-coat RAL 9006 finish
  • Louvred ventilation, HVAC or liquid-cooling interface to your rack supplier
  • Fire-rated partition and detection, per the strategy your insurer accepts
  • 35 days typical build · one unit is a valid order

Built to order. Send the rack datasheet and the site ambient; the enclosure is sized
around them.

gallery
RELATED PRODUCT
Card Eq Shell
Custom Equipment Shell — Cuts, Doors, Coating and Insulation to Your Drawing
Card Eq Lab V2
Mobile Laboratory Container — Fume Extraction, Bench and a Sink That Drains
Telecom equipment shelter with louvre panels (catalogue crop)
Telecom & Edge Equipment Shelter — Walk-In, IP55, DC Powered
Card Eq Ctrl V2
Connection & Control Room — Cable Terminations, PLC and a Desk Somebody Can Sit At
Contact us

Committed to providing customers with high-quality and reliable container solutions.