Water Treatment Container — Filtration, Dosing and Pump Sets Pipeless on Site

Water Treatment Container — Filtration, Dosing and Pump Sets Pipeless on Site

Categories:

Filtration, dosing and pump sets piped and wet-tested in the yard, on a floor that slopes to a drain and sleeves cut before the lining went in.

10–40 ftshell
5–50 m³/hflow
±0.5pH control
C4corrosion
01 / OVERVIEW

What it is for

A water treatment plant in a container is a process skid with a roof. What makes it work is not the membrane or the dosing pump — it is the floor that slopes to a drain, the pipe penetrations that were cut before the lining went in, and the fact that somebody piped it in a factory instead of on a wet site.

We build the room and the process skid inside it: filtration, dosing, pumps, controls, drainage and the frost protection the site needs. The process design is agreed with you or your water engineer, and we do not pretend to be the process designer.

Where these units go is where a plant room cannot: mining camps, construction villages, resorts on an island, and factories that need to prove pre-treatment before discharge. In all four cases the container is the reason the project is possible, not a cost saving.

Where it is typically used

Construction and mining campsPotable water for 50–500 people, with filtration, disinfection and a storage tank.
Resorts and remote hospitalityWhere the borehole is brackish and the alternative is bottled water.
Industrial pre-treatmentpH correction, oil separation and dosing before discharge to a municipal sewer.
Emergency responseA plant that arrives on a truck and produces water the same week.
02 / SPECIFICATIONS

Key specifications

Shell 10 / 20 / 40 ft, or a 40 ft high cube for tall skids
Flow range 5–50 m³/h depending on process, stated per project
Process Sand or multimedia filtration, carbon, softening, RO, UV or dosing as required
Dosing Chemical dosing skid with duty and standby pumps, bunded chemical store
Pump set Duty and standby, 2–15 kW, with dry-run protection
Floor Sloped to a drain, epoxy-coated, bunded where chemicals are stored
Penetrations Welded pipe sleeves, spare ways capped, all cut before lining
Drainage Internal gully to a site connection, with a sample point
Frost protection Trace heating and insulation for cold sites; ventilation for hot ones
Controls PLC with HMI, dosing proportional to flow, alarm contacts to the site system
Corrosion C4 standard; stainless wetted parts where the water demands it
Design ambient −30 °C to +50 °C, stated in the contract

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Process skid

Filtration vessels, membranes or dosing tanks on a frame that was piped and pressure-tested in the yard.

02Pump set

Duty and standby pumps with dry-run protection, isolation valves and a drain.

03Chemical store

Bunded compartment, separate ventilation, signage and a spill kit.

04Floor and drainage

Sloped epoxy floor, gully, sample point and a discharge connection.

05Penetrations and pipework

Welded sleeves and pre-fabricated pipe spools so site work is connection, not fabrication.

06Controls

PLC and HMI, dosing proportional to flow, remote alarm contacts.

04 / MODELS

Which model to take

Model Shell Flow Process Use
EQ-WT-10 10 ft · 2,991 mm 5–10 m³/h Filtration + UV Small camp, single borehole
EQ-WT-20 20 ft · 6,058 mm 10–25 m³/h Filtration + carbon + dosing Camp, resort
EQ-WT-40 40 ft · 12,192 mm 25–50 m³/h Multimedia + RO + dosing Industrial, mining
EQ-WT-40D 40 ft · two rooms 25–50 m³/h Process + chemical store Where chemicals must be separated

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

The floor slope and the pipe sleeves are decided before the lining goes in

ENGINEERING NOTE

Cut once, in the right place

A container is a finished, painted, insulated object. Every hole cut after lining means opening the vapour barrier, resealing a coated edge and hoping the seal holds for fifteen years. It is also the most common source of leaks in process containers.

So we ask for the pipe schedule and the drain position before we cut, and we cut spare ways at the same time. A capped spare sleeve costs a few dollars; a hole cut on site costs a day and a warranty argument.

Slope is not a detail

A flat floor in a wet room becomes a puddle, and a puddle in a steel box becomes a corrosion cell within a season. Our standard process floor slopes to a gully at 1:100 with an epoxy coating, and the bund around the chemical store is part of the same casting rather than a tray dropped in afterwards.

Penetration and drainage drawings are issued for approval before the shell is cut. Cutting after lining is possible and always visible.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

You have a water analysis and a flow requirement.

Those two documents define the process and the skid.

The site has no building and no plant room.

A container arrives finished and piped.

The plant must move later.

Lift it, take it with you, reconnect.

The water is heavily contaminated with solvents or heavy metals.

That is a specialist process design; we will build the room, but the process must be engineered by a water specialist.

You need 200 m³/h.

At that size a site-built plant is cheaper than a container.

07 / DELIVERY

From contract to energisation

Data

Water analysis, flow, discharge limits, chemical list, site climate.

Process

Process design and P&ID agreed in 7–10 days, with your engineer or ours.

Contract

Drawing release, deposit, long-lead items (membranes, pumps) ordered.

Production

35–55 days: shell, lining, penetrations, skid, pipework, wet test in the yard.

Commissioning

Wet test before dispatch, then site commissioning with a water sample at handover.

08 / GALLERY

On site and in detail

Water treatment containers installed outdoors in a row
Water treatment containers installed outdoors in a row
Process skid with pumps and manifolds piped in the yard
Process skid with pumps and manifolds piped in the yard
Bunded floor and drainage detail inside a process container
Bunded floor and drainage detail inside a process container
Equipment containers staged before connection
Equipment containers staged before connection

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Do you design the water process?

We design filtration and dosing plants ourselves and work with your water engineer on RO and specialist processes. We will not pretend to be the process authority on a difficult water.

Can the chemical store be in the same box?

Only with a separate compartment, separate ventilation and bunding. On a 40 ft shell we build two rooms; on a 20 ft we put the store outside.

What happens in winter?

Trace heating and insulation on the pipework, and a drain-down procedure in the O&M file. A container does not freeze-proof itself.

Is it tested before shipment?

Wet tested in the yard with real water, and the test sheet travels with the unit. Membranes are preserved and the preservation record is in the file.

Can we add capacity later?

On a 40 ft shell, usually yes — spare ways and space for one more vessel. On a 20 ft, usually not, and we will say so at quotation.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the enclosure range

Product Details

A plant room that ships in one piece

Pumps, membranes, dosing skids and controls all arrive in one enclosure with the pipe penetrations
already cut, the floor falls already formed and the drain already going somewhere. Site work becomes
connections rather than construction.

Where it is used

Remote camps that cannot rely on a municipal supply, construction villages, and industrial sites
discharging to a consent level. Because the train is inside a container, it can be relocated when the
camp moves — and it can be tested at the factory before it ever sees dirty water.

Key figures

  • 20 ft and 40 ft shells · open or partitioned layouts
  • Floor falls, drains and bunded chemical zones formed in the shell
  • Pipe and cable penetrations cut to your P&ID
  • Insulated and ventilated for the climate it works in
  • Factory assembly and wet test before shipment

Built to order. Send the P&ID and the flow rate; the shell follows the train.

gallery
RELATED PRODUCT
Card Eq Haz
Hazardous Waste & Chemical Store — Bunded, Ventilated, Signage That Passes Inspection
Card Eq Skid
Skid Base & Lifting Frame — ISO Corners, Lifting Lugs, Sea-Fastened
Battery energy storage containers on site (catalogue crop)
Battery Energy Storage Container — 10, 20 and 40 ft with Fire and Thermal
Telecom equipment shelter with louvre panels (catalogue crop)
Telecom & Edge Equipment Shelter — Walk-In, IP55, DC Powered
Contact us

Committed to providing customers with high-quality and reliable container solutions.