Power Module (UPS & Distribution)

Power Module (UPS & Distribution)

UPS, LV distribution and automatic transfer in one 200–800 kVA enclosure, one busbar run from the IT module.

200–800kVA
96% double-conversion
99% ECO
15s to generator load
01 / OVERVIEW

What it is for

Electricity is the one thing a data centre cannot lose. Servers can be clocked down, workloads can migrate, but a power cut takes everything.

The power module handles three jobs: absorbing utility instability with the UPS, transferring between two incoming supplies with the ATS, and distributing to each rack.

Putting the three in one enclosure shortens the wiring, cuts losses and simplifies servicing. The downside is concentrated heat. A 400 kVA UPS at full load loses more than ten kilowatts, all of it as heat, and it has to go somewhere.

So the power module normally does not share cooling with the IT module. It gets a small dedicated unit, or ducted extract to outside.

Where it is typically used

Paired with IT modules as one systemA single busbar run between them, with maintenance on one not affecting the other.
Electrical upgrade in an existing hallAgeing UPS and too few outgoing circuits: replacing the whole enclosure is faster than reworking panel by panel.
Core site requiring 2NDual incoming supply, dual busbars and an independent ATS, with the two paths physically separated.
02 / SPECIFICATIONS

Key specifications

UPS capacity 200 / 400 / 600 / 800 kVA, modular N+1
UPS type Double-conversion online, IGBT rectifier
Efficiency 96% double conversion, 99% in ECO
Input 380/400 V three-phase four-wire, THDi below 3%
Output 380/400 V, voltage regulation ±1%
Transfer ATS with 1–10 s adjustable transfer time
Distribution Incoming, metering, outgoing and rack panels
Outgoing circuits 12–36, configured to rack count
Protection IP54, internal temperature control and extract
Monitoring Per-circuit current, power and energy over Modbus TCP or SNMP

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01UPS

Modular power units, N+1, each module hot-swappable.

02Battery interface

DC bus to an external battery module, with fuses and a DC breaker.

03ATS panel

Two-supply changeover, mechanically interlocked against paralleling.

04LV distribution

Incoming, metering, outgoing and bus-tie, copper rated to 800 A.

05Rack panels

One circuit per rack with individual metering, A and B outputs.

06Controls

Local touch screen, Modbus and SNMP to the monitoring system.

04 / MODELS

Which model to take

Model UPS rating Active power Outgoing circuits Supply
AIDC-PWR200 200 kVA 200 kW 12 Single
AIDC-PWR400 400 kVA 350 kW 24 Single / dual
AIDC-PWR800 800 kVA 700 kW 36 Dual 2N

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Double conversion or ECO: is the 3% worth having

ENGINEERING NOTE

What the two modes do

Double conversion (online): utility power is rectified to DC and inverted back to AC. The DC bus in between blocks voltage sag, frequency deviation, harmonics and surges from reaching the load. The price is two conversion stages, each losing a little, giving about 96% overall.

ECO mode: in normal operation the load runs on the bypass, and the inverter idles on standby. When the supply goes out of tolerance the load transfers to the inverter in 2–4 ms. Efficiency reaches 99%, because only the bypass switch and filter are in the path.

The three points between them, on a 400 kVA UPS at 70% load, is 8.4 kW. Over 8760 hours that is 74,000 kWh. At 0.10 USD per kWh, about 7,400 USD a year.

What the saving costs

In ECO the load sees the raw utility supply. Voltage sags, lightning surges and frequency swings land directly on the server power supplies. Those supplies tolerate some of it, not all of it.

The transfer itself is the sharper problem. Two to four milliseconds is fine for most server supplies, which hold up for 10–20 ms. But if the load includes legacy equipment, industrial PCs or non-standard supplies, some of it will reboot.

The industry convention: where servers dominate and supply quality is good, ECO is defensible. Where there is industrial equipment, medical equipment or old kit, use double conversion and accept the loss.

And one more: many grids are simply not clean enough for ECO. Where voltage deviation exceeds ±10% or harmonic distortion is out of limits, ECO passes all of it to the load, and the electricity saved does not cover the equipment it damages.

The transfer chain

Utility fails, UPS takes over: 0 ms, since double conversion was already supplying the load.

UPS carries the load while the ATS sees the loss and transfers to the generator side: 1–10 s, adjustable.

Generator starts, builds voltage, closes: 10–15 s, with most standards requiring 15 s and good sets achieving 8–10.

The three stages add up to 25 s worst case. That is why autonomy is not set at five minutes. Fifteen minutes allows for a failed start and a second attempt.

Whether ECO can be enabled depends on two things: grid quality and the type of load. If either is uncertain, leave it off. A 3% saving does not pay for one outage.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

2N required, independent servicing wanted

UPS and distribution in their own enclosure, so servicing does not disturb the IT module.

Under 150 kVA

The fixed cost of a dedicated enclosure is high. A UPS inside the IT module is better value.

IT and battery modules already in place, power missing

Buy the power module alone and connect busbar and DC cable.

Hot site with poor ventilation

A fully loaded UPS loses over ten kilowatts. Internal temperature will pass 45 °C, so add cooling or forced extract.

07 / DELIVERY

From contract to energisation

Confirmation · 3 days

Capacity, circuit count, 2N or not, ATS type.

Drawings · 1 week

Single-line diagram, panel layout, entry and exit positions.

Production · 4–5 weeks

Panel assembly, copper fabrication, wiring, dielectric test.

FAT · 2 days

Full-load temperature rise, transfer test, protection settings.

Site · 3–5 days

Placement, busbar and battery connection, on-load commissioning.

08 / GALLERY

On site and in detail

Inside the power module: UPS, LV distribution and ATS in a row
Inside the power module: UPS, LV distribution and ATS in a row
Battery racks and the DC bus interface
Battery racks and the DC bus interface
Lifting a power module, noting the rearward centre of gravity
Lifting a power module, noting the rearward centre of gravity
Electrical parameters reported to the monitoring room
Electrical parameters reported to the monitoring room

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Does the UPS have to be modular?

We recommend it. Modules can be added as load grows, and a failed module is swapped hot without stopping the UPS. Transformer-based monobloc units are cheaper but need a shutdown to repair, which is why they are rarely specified now.

What is the difference between ATS and STS?

An ATS is a mechanical switch with a 1–10 s transfer, used between utility and generator. An STS is static, transferring in 4–8 ms, used between two utility sources. Where no interruption is acceptable, use an STS and pay for it.

What if there are not enough outgoing circuits?

Add rack panels. The main enclosure goes to 36 circuits; beyond that add a panel enclosure, or distribute at the IT module.

Must batteries be in a separate enclosure?

Above 200 kWh, yes. Lithium has high energy density, and next to switchgear a fire is much harder to fight.

Can it be installed outdoors?

It is an outdoor product at IP54. Watch internal temperature: in summer sun the enclosure reaches 55 °C and the UPS derates. Add a sunshade or forced ventilation.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the full range

Product Details
gallery
RELATED PRODUCT
AIDC skid — main image
Prefabricated IT Skid
AIDC fire — main image
Fire Suppression & Auxiliary Module
AIDC pair20 — main image
20 ft Twin-Module Data Centre
AIDC cluster — main image
Prefabricated Data Centre Cluster
Contact us

Committed to providing customers with high-quality and reliable container solutions.