Battery Module

Battery Module

100–500 kWh of lithium iron phosphate in its own enclosure with independent suppression, giving the UPS 15–30 minutes of autonomy.

100–500kWh
15–30minutes autonomy
6000cycles
standalonegas suppression
01 / OVERVIEW

What it is for

A UPS stores nothing. How long it rides through an outage depends entirely on the battery.

Ten years ago every data centre used lead-acid. New build is almost all lithium iron phosphate, for a simple reason: for the same capacity, lithium takes a third of the space and a quarter of the weight, and cycles six to ten times longer.

The price is a higher safety requirement. Lithium cells can enter thermal runaway, and once it starts the temperature passes 800 °C and the fire can re-ignite. So the battery module must be independent: its own detection, its own suppression, its own pressure relief, and a fire wall between it and the IT modules.

We put cells, BMS, suppression and cooling in one enclosure and complete a charge-discharge test before dispatch. On site, connect the DC cable and it is ready.

Where it is typically used

Extending an existing UPSThe original autonomy is too short, and an extra enclosure is cheaper than replacing the UPS.
Replacing lead-acid with lithiumSame capacity in a third of the floor area, with a much lower floor loading.
Thirty minutes of autonomy requiredWhere generators are unreliable or not permitted to start, the battery carries the site.
02 / SPECIFICATIONS

Key specifications

Chemistry Lithium iron phosphate (LFP); NCM available but not recommended
Capacity 100 / 200 / 300 / 500 kWh
DC voltage 480 V / 512 V / 600 V to match the UPS
Autonomy 15 / 30 minutes, set by load
Cycle life 6000 cycles at 80% depth of discharge, 25 °C
BMS Three levels: cell, module, string, with balancing and insulation monitoring
Fire FK-5-1-12 plus optional water sprinkler, dual detection interlock
Temperature Precision cooling at 18–27 °C, gradient within 5 °C
Protection IP54 with independent pressure relief
Communication CAN and Modbus TCP to monitoring and UPS

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Battery racks

Standard 19-inch racks, 4–8 modules each, copper busbar connection with fuse protection.

02Battery modules

LFP cells with module-level BMS sampling temperature and voltage.

03BMS controller

String-level management, SOC and SOH estimation, disconnection on fault.

04Cooling

Precision unit holding 18–27 °C, since heat accelerates capacity fade.

05Fire

FK-5-1-12 cylinders, smoke and heat detection, explosion-proof relief, sounder beacons.

06DC distribution

DC breakers, fuses, insulation monitoring and earth fault protection.

04 / MODELS

Which model to take

Model Capacity Autonomy Racks Fire
AIDC-BAT100 100 kWh 15 min at 400 kW 2 racks FK-5-1-12
AIDC-BAT200 200 kWh 30 min at 400 kW 3 racks FK-5-1-12 + water
AIDC-BAT500 500 kWh 30 min at 1000 kW 6 racks FK-5-1-12 + water

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Lithium or lead-acid, and how thermal runaway is actually contained

ENGINEERING NOTE

Start with the arithmetic

For 200 kWh of usable capacity, lead-acid is sized at 50% depth of discharge, so 400 kWh installed: about 20 m² of floor and 12 tonnes. LFP at 90% depth of discharge needs 220 kWh: about 7 m² and 2.5 tonnes.

Lead-acid is cheaper up front, roughly 55%–65% of the lithium price. But it lasts 300–500 cycles, so four or five years and it is replaced, while lithium at 6000 cycles lasts over a decade at one cycle a day.

Add replacement, floor area and structural strengthening into a ten-year total cost of ownership and lithium usually lands at 60%–70% of lead-acid. For new build there is not much to debate.

What thermal runaway is

An internal short heats the cell locally, the electrolyte decomposes and vents gas, temperature climbs, and neighbouring cells ignite. Once that sequence starts, external suppression struggles to stop it. You cool, you isolate, and you wait for it to finish.

LFP decomposes at 250–300 °C; NCM at 150–200 °C. That is why data centres use LFP and not NCM: NCM stores more energy per kilogram but is thermally less stable.

The trigger is usually mechanical damage, electrical abuse such as overcharge or an external short, or local overheating. So protection is layered: impact protection in the structure, overcharge protection in the BMS, and local temperature control in the cooling system.

What makes suppression effective

First, early detection. Smoke, heat and gas detection (CO and H2) together give three to five minutes more warning than smoke alone, and those minutes decide whether the fault can be isolated before runaway.

Second, disconnection. On detection the BMS opens the affected string and the panel shuts the DC path, stops cooling and starts extract.

Third, suppression. FK-5-1-12 works by absorbing heat and chemically interrupting the flame, discharging in about ten seconds with a ten-minute hold. Against lithium re-ignition it is not enough on its own, so a water sprinkler is normally added for sustained cooling. That is why large battery modules get a water system.

Fourth, pressure relief. The enclosure must have a relief vent sized to code and aimed away from walkways. In a deflagration the pressure needs somewhere to go, or the enclosure deforms and the door leaves the frame.

One thing that gets overlooked

Temperature. Lithium fades slowest at 25 °C, loses roughly half its life above 35 °C, and above 45 °C ages faster with a safety penalty attached. So the battery module needs its own cooling, and cannot share with the IT module: IT runs at 22 °C, batteries at 25 °C, and the requirements differ.

Humidity matters too. Too high causes tracking, too low causes static. 40%–60% is the workable band.

Do not let batteries share space with switchgear. A lithium fire produces flammable gas, and switchgear arcs are a ready ignition source.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

New build with a ten-year-plus horizon

LFP is the only sensible choice.

Very tight budget, five minutes of ride-through only

Lead-acid still works, but accept replacement every four or five years.

Over 200 kWh

A dedicated enclosure is essential, with water sprinkler and gas suppression.

Site consistently above 40 °C with no cooling

Lithium life halves. Fix the temperature before discussing capacity.

07 / DELIVERY

From contract to energisation

Confirmation · 3 days

Capacity, autonomy, DC voltage, water sprinkler or not.

Drawings · 1 week

Rack layout, DC routing, fire pipework.

Production · 4–5 weeks

Enclosure, fire, cooling, battery integration.

FAT · 3 days

Charge-discharge test, BMS integration, fire interlock.

Site · 3 days

Placement, DC cable connection, communication commissioning.

08 / GALLERY

On site and in detail

Inside a battery module: racks, BMS, suppression cylinders
Inside a battery module: racks, BMS, suppression cylinders
Cylinder bank and pipework with independent zone valves
Cylinder bank and pipework with independent zone valves
DC cable entry into the power module
DC cable entry into the power module
Fire separation between battery and IT enclosures
Fire separation between battery and IT enclosures

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Can the battery module go indoors?

Yes, subject to fire compartmentation and pressure relief. Most projects put it outside on its own foundation, at least 3 m from other modules.

When do the batteries need replacing?

At 6000 cycles and one cycle a day, 12–15 years. In practice you replace when SOH reaches 80%, which means evaluating around year ten.

Can second-life cells be used?

Technically yes, but not where reliability matters. Consistency and remaining life are unknown and the BMS becomes difficult to tune.

How long does the factory test take?

One full charge-discharge cycle, about 6–8 hours, recording capacity, internal resistance and temperature rise. Customers may witness.

What does fire acceptance check?

Detection interlocks, a discharge test using nitrogen, relief vent area, fire separation and escape routes. Requirements vary by jurisdiction.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the full range

Product Details
gallery
RELATED PRODUCT
AIDC gen — main image
Generator Module
AIDC cool — main image
Cooling Module
Edge data centre container on a concrete pad (catalogue crop)
20 ft Edge Data Centre
Prefabricated IT modules lined up at the factory (catalogue crop)
IT Module (Rack Module)
Contact us

Committed to providing customers with high-quality and reliable container solutions.