Fire Suppression & Auxiliary Module

Fire Suppression & Auxiliary Module

Clean-agent cylinders, manifolds and the alarm panel in one enclosure, covering up to 3000 m³ of IT modules.

10s discharge
10min hold
3agents available
1panel for the site
01 / OVERVIEW

What it is for

Fire in a data centre involves energised equipment of high value, and it rules out conductive agents. Water shorts it, powder contaminates it, foam is worse. What is left is clean agent: no residue, non-conductive, and it does not damage the equipment.

The fire module gathers the cylinders, valve manifolds and alarm panel into one enclosure, with pipework distributed to each IT module.

A 6 MW campus can need several dozen cylinders. Distributed across every IT module, that consumes space, complicates inspection and makes unified management difficult. One dedicated enclosure is more practical.

The enclosure itself needs fire compartmentation, independent ventilation, and warning signage with an emergency abort button at the door.

Where it is typically used

Central suppression for a multi-module clusterCylinders in one enclosure, pipework to each IT module, managed as one system.
Independent suppression for a single enclosureOne enclosure, one system, no dependence on anything outside.
European delivery requiring an environmentally acceptable agentHFC-227ea is restricted under F-gas rules, so FK-5-1-12.
02 / SPECIFICATIONS

Key specifications

Protected volume By total IT module volume, up to 3000 m³ per system
Agent HFC-227ea / FK-5-1-12 / IG-541
Design concentration 7%–8% HFC-227ea, 4.5%–5.5% FK-5-1-12, 40% IG-541
Discharge time 10 seconds or less
Hold time 10 minutes or more
Detection Smoke and heat, with discharge only on dual alarm
Actuation Automatic, manual and mechanical emergency, three levels
Cylinders 40 L / 70 L / 80 L, sized to volume
Protection Independent compartment, 60-minute fire rating

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Cylinder bank

Cylinders, racks, head valves and safety relief devices.

02Manifold

High-pressure hoses, check valves, manifold and selector valves.

03Pipework

Galvanised steel or stainless, run to the nozzles in each IT module.

04Alarm panel

Dual-loop detection, sounder beacons, interlock control, event log.

05Release control

Solenoid actuation, manual pull ring, mechanical emergency.

06Pressure relief

Area to code, positioned away from walkways.

04 / MODELS

Which model to take

Model Agent Protected volume Cylinders Notes
AIDC-FIRE-H7 HFC-227ea 1500 m³ 8 Best value
AIDC-FIRE-N5 FK-5-1-12 2000 m³ 10 Low GWP, export default
AIDC-FIRE-IG IG-541 3000 m³ 24 Large volume, no GWP

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Three agents, and how to choose without getting caught out

ENGINEERING NOTE

HFC-227ea (FM-200)

The most widely used, fast, discharging in about ten seconds at a design concentration of 7%–8%. Few cylinders, small footprint, moderate cost.

The problem is a global warming potential of 3220, nearly 3000 times that of CO2. The EU F-gas regulation already restricts new installations, and several US states are following.

So for European delivery it is effectively unavailable. China has no nationwide ban yet, but more owners exclude it in tender documents every year.

FK-5-1-12 (Novec 1230)

GWP of 1 and an atmospheric lifetime of five days, which makes it the most environmentally acceptable chemical agent available. Design concentration 4.5%–5.5%, lower than HFC-227ea, so fewer cylinders again.

It costs more, roughly 1.3–1.5 times HFC-227ea. In exchange there is almost no residue after discharge, which suits precision equipment.

For Europe, North America and Australia, specify this from the start and avoid a retrofit later.

IG-541 (Inergen)

A blend of 52% nitrogen, 40% argon and 8% CO2, extinguishing by bringing oxygen down to about 12.5%, a level people can still breathe.

No global warming potential, no decomposition products, and refillable. The drawback is 200–300 bar storage, so roughly three times as many cylinders, a larger footprint and high-pressure pipework.

It suits large volumes and projects with the strictest environmental requirements. Containerised data centres rarely use it because the cylinders will not fit.

The double interlock

Codes require two independent detectors to alarm before discharge, known as double interlock, to prevent accidental release.

Anyone who has commissioned a project knows the accidental releases are mostly not detector faults but construction and commissioning: dust from building work triggering smoke detection, welding triggering heat detection, and someone forgetting to switch to manual during testing.

So switch to manual during commissioning and run a nitrogen discharge test before handover. A single accidental HFC-227ea discharge costs tens of thousands, and the industry manages it every year.

Do not use HFC-227ea on export projects. The EU F-gas regulation already restricts it and parts of North America are following, and retrofitting means new cylinders, new valves and a fresh approval.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

Export to Europe or North America

Specify FK-5-1-12: compliant, and no retrofit later.

Very tight budget, domestic project

HFC-227ea still works, but confirm there is no local restriction.

Protected volume above 3000 m³

IG-541 suits this better; more cylinders, but stable pressure per unit.

Small containerised hall

IG-541 cylinders will not fit. Use HFC-227ea or FK-5-1-12.

07 / DELIVERY

From contract to energisation

Volume calculation · 2 days

Net volume, opening compensation, design concentration.

Design · 1 week

Cylinder count, pipework, nozzle layout, relief vent.

Production · 3–4 weeks

Enclosure, racks, prefabricated pipework, alarm system.

FAT · 1 day

Pipework pressure test, interlock logic, simulated discharge.

Site · 3–5 days

Pipework connection, nozzle installation, integrated commissioning.

08 / GALLERY

On site and in detail

Inside the fire module: cylinders, manifold, alarm panel
Inside the fire module: cylinders, manifold, alarm panel
Separate suppression zone in the battery module
Separate suppression zone in the battery module
Nozzles and detection at the ceiling of an IT module
Nozzles and detection at the ceiling of an IT module
Fire alarms reported to the monitoring room
Fire alarms reported to the monitoring room

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

How many IT modules can one system cover?

By total volume rather than module count, up to 3000 m³ per system. Above that, split into separate systems. Each IT module needs its own selector valve so it can discharge independently.

How soon can you enter after discharge?

HFC-227ea and FK-5-1-12 need 10–15 minutes of ventilation to fall below the safe concentration. IG-541 is made of atmospheric gases, so ventilation is quicker.

Do cylinders need annual inspection?

Yes. Check pressure and weight annually, and hydrostatic test every five years, ten in some codes. A weight loss above 5% means top-up or replacement.

Can it share a panel with the sprinkler system?

Yes, but on a separate loop. Gas suppression and sprinkler interlocks work on completely different logic, and combining them invites spurious operation.

What does acceptance check?

The concentration calculation, cylinder certificates, pipework pressure test records, interlock test records and relief vent area. Miss one and it will not pass.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the full range

Product Details
gallery
RELATED PRODUCT
AIDC power — main image
Power Module (UPS & Distribution)
AIDC pair20 — main image
20 ft Twin-Module Data Centre
Edge data centre container on a concrete pad (catalogue crop)
20 ft Edge Data Centre
Prefabricated IT modules lined up at the factory (catalogue crop)
IT Module (Rack Module)
Contact us

Committed to providing customers with high-quality and reliable container solutions.