20 ft Edge Data Centre

20 ft Edge Data Centre

A 20 ft edge data centre for three or four racks beside a mast, a production line or a shop, running unattended on ten minutes of battery.

3–4racks
150kVA UPS
10minutes autonomy
−25 to 50°C ambient
01 / OVERVIEW

What it is for

An edge site is not chosen by people, it is chosen by the service. The radio needs to be at the mast, the line needs to be at the workshop, the till needs to be at the counter. None of those places has a data room, and often not a decent building either.

A 20 ft enclosure occupies 6 m² of ground. It can be set beside a verge, in the corner of a workshop or on a roof deck. Connect 380 V three-phase and one fibre and it is live the same day.

Inside are three or four racks carrying switches, servers, storage and inference cards. A 150 kVA UPS rides through ten minutes, long enough to start a generator or shut the service down cleanly.

These sites are empty almost all the time, so the design goal is not ease of maintenance, it is no maintenance: out-of-band management, auto-restart on power return, environmental alarms, and access granted remotely.

Where it is typically used

Compute node beside a radio mastFibre is there and the building is not. Get the equipment running and deal with civil works later.
Machine vision in a workshopSeveral cameras inferring locally and sending only results back to the centre.
Local servers in a retail chainPoint of sale, stock and CCTV running locally, so the shop still trades when the link drops.
Tiered dispatch along highways and portsNodes distributed along the route, unattended, managed remotely.
02 / SPECIFICATIONS

Key specifications

Enclosure size 5.90 × 2.35 × 2.39 m (20 ft standard)
Racks 3 standard / 4 in the compact layout
Power per rack 8–25 kW
Total IT load 100–150 kW
UPS 150 kVA modular, 10 minutes autonomy
Cooling 1 × 25 kW precision unit plus standby, or 2 × 12.5 kW
Air distribution Front supply, rear return, separated paths
Fire 2 × 40 L HFC-227ea, dual detection interlock
Protection IP55, roof snow load 1.5 kN/m²
Ambient temperature −25 °C to +50 °C, cold-weather package optional
Monitoring Environmental, out-of-band management, 4G/5G backhaul
Unattended operation Remote power cycling, remote KVM, remote door release

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

0120 ft enclosure

2.0 mm corrugated skin, 100 mm rock wool, steel base with fork pockets and lifting lugs.

02Rack zone

Three 42U racks, perforated doors, dual PDU per rack, top cable trunking.

03Power zone

150 kVA UPS, incoming distribution, surge protection and metering at one end.

04Cooling

25 kW precision unit with remote condenser, condensate pumped out.

05Fire

Two 40 L HFC-227ea cylinders, pre-action valve, smoke and heat detection, pressure relief.

06Monitoring

Temperature, humidity, leak, door contact, smoke and UPS status, all over one 4G link.

04 / MODELS

Which model to take

Model Racks IT load UPS Cooling Type
AIDC-20E3 3 150 kW 150 kVA 25 kW Standard
AIDC-20E4 4 150 kW 150 kVA 2 × 12.5 kW Compact
AIDC-20EC 3 100 kW 100 kVA 12.5 kW Cold region, trace heated

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

The latency arithmetic at the edge, and what unattended really means

ENGINEERING NOTE

Where the latency actually goes

Light travels through fibre at about 5 microseconds per kilometre, so 10 microseconds round trip. A data centre 100 km away costs 1 ms on the glass. That does not sound like much.

But the glass is not the whole path. Data crosses switches at 5–20 microseconds per hop, a firewall at 50–200 microseconds, a load balancer, and then the server processes it. A cross-city round trip of 2–5 ms is normal; cross-province reaches 20–40 ms.

Why does industrial control care? A PLC scan cycle is 10–20 ms and closed-loop control works in milliseconds. A 5 ms round trip to the cloud has already eaten a quarter of the budget, and jitter makes the loop unstable. Compute running the line has to sit next to the line.

Video analytics is the same argument. One 4K stream is 8 Mbps, ten of them are 80 Mbps, and sending all of that back costs bandwidth and storage. Sampling frames locally, inferring locally and returning only results is the standard edge pattern.

Unattended is designed, not announced

The first layer is out-of-band management. If the operating system hangs but the BMC is alive, you can power cycle, enter the BIOS and mount a virtual disk to reinstall. Without that layer, someone has to drive there.

The second layer is environmental self-recovery. When utility power returns, the UPS restarts, the cooling restarts, and servers power up in sequence so they do not all surge at once. Plenty of halls skip sequenced start and trip the breaker on the first recovery.

The third layer is alarm severity. Two degrees above setpoint and ten degrees above setpoint should not send the same message. Ours defaults to three levels: information, logged; warning, emailed; critical, phoned. Too many messages is the same as none.

The fourth layer is physical access. Grant a single door opening remotely, valid once, then expired. Considerably safer than a key held by a regional manager.

Where the real risk sits

Not in equipment failing, but in nobody knowing it failed. A central hall has 24/7 cover; an edge node may go three months without anyone looking at it.

So the monitoring path has to be independent. If the service network is down, monitoring still has to report, which means its own 4G link rather than sharing the service fibre. This is the line most often cut, and it is exactly the line you need when something goes wrong.

Then there is the environment. An outdoor enclosure sees sun, standing water, animals and dust that a machine room never does. IP55 is the floor, cable entries must be sealed, and the base needs a rodent plate.

Give an edge node its own 4G backhaul rather than sharing the service fibre. When the service link drops and monitoring is still reporting, that link has paid for itself.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

Beside a mast, at the end of a line, behind a shop, three racks or fewer

A 20 ft footprint and lifting weight suit these sites, and it is live in a day.

More than five racks

A 20 ft enclosure will not take them. Move to 40 ft or a twin-module pair.

No local maintenance staff

Out-of-band management, graded alarms and remote access cover the gap until someone arrives.

Over 30 kW per rack

Air cooling cannot cope and there is no room for liquid pipework. Use the liquid-cooled AIDC-IT.

07 / DELIVERY

From contract to energisation

Confirm requirements · 3 days

Rack count, power per rack, backhaul method, cold and heat requirements.

Drawings · 5 days

Layout, single-line diagram, foundation and interface drawings.

Production · 3–4 weeks

Enclosure conversion, assembly, wiring, pressure testing.

FAT · 1 day

Load test, fire interlock, remote management integration.

Transport and placement · 2–3 days

Standard flatbed, positioned by forklift or an 8 t crane.

08 / GALLERY

On site and in detail

20 ft edge node installed beside a telecoms mast
20 ft edge node installed beside a telecoms mast
Twin-module pair, IT and power in separate enclosures
Twin-module pair, IT and power in separate enclosures
Contained aisle and perforated floor
Contained aisle and perforated floor
Whole-enclosure lift; on a 20 ft module a forklift can replace the crane
Whole-enclosure lift; on a 20 ft module a forklift can replace the crane

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

How much ground does it need?

The enclosure is 14 m². Allow 30 m² with service clearance and the condenser. A hardstanding or a 150 mm concrete slab is enough.

What supply does it need?

150 kW of IT load plus cooling comes to about 200 kVA, so a 250 kVA transformer. Two feeds are better, one works.

Can I leave out the generator?

Yes. Edge nodes are usually specified as utility plus 10 minutes of UPS, with the service degrading or migrating elsewhere. Whether you need a generator depends on whether the service can accept an outage.

Will it freeze in winter?

The standard build is rated to −25 °C. Colder needs a cold-weather package: trace heating on pipework, battery heating, crankcase heaters. Priced separately.

How is remote management connected?

A dedicated 4G router inside the enclosure links to the monitoring controller and the server BMCs. The customer side needs a VPN or a port forward. No public IP required.

What happens when something fails?

The design is modular: UPS power modules, cooling units and PDUs are all field replaceable. Keep a spares kit inside the enclosure; there is a cabinet for it.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the full range

Product Details

Compute where the cable lands

A 20 ft shell with the same architecture as the 40 ft unit at a quarter of the footprint: changeover,
UPS, in-row cooling, detection and suppression, all pre-piped and pre-terminated. It goes on a slab, a
roof or a trailer, and it is running the same week it arrives.

Where it earns its keep

At the edge of a mobile network, behind a factory gate, beside a wind farm — anywhere latency or
a rented line makes a central hall the wrong answer. Two units give you an N+1 pair without a second
building permit. Where a site is temporary, the box leaves with you.

Key figures

  • 20 ft ISO shell · single-aisle rack layout to your schedule
  • Integrated UPS, PDU and branch protection · ratings quoted to the load
  • In-row or wall-mounted precision cooling · outdoor condensing unit
  • Detection and clean-agent suppression inside the shell
  • Factory-tested power, cooling and monitoring loops before shipment

Built to order. Rack count and UPS rating are set by your load schedule, not by a catalogue.

gallery
RELATED PRODUCT
AIDC gen — main image
Generator Module
AIDC battery — main image
Battery Module
AIDC cluster — main image
Prefabricated Data Centre Cluster
Prefabricated IT modules lined up at the factory (catalogue crop)
IT Module (Rack Module)
Contact us

Committed to providing customers with high-quality and reliable container solutions.