Enclosure HVAC & Ventilation — Cooling, Explosion-Proof Fans, Motorised Louvres

Enclosure HVAC & Ventilation — Cooling, Explosion-Proof Fans, Motorised Louvres

Categories:

Enclosure cooling and ventilation from 3 to 25 kW, louvre free area calculated, ATEX fans and interlocked controls where the area is classified.

3–25 kWcooling
IP55unit
−40 °Ccold start
ATEXfans on request
01 / OVERVIEW

What it is for

An enclosure is only as good as the air going through it. A sealed box cooks; a box with the wrong louvre area shorts its own cooling; and a box with an unsealed penetration fills with dust in a season.

We supply and fit the air side as a system: cooling sized to the loss figure, ventilation sized to the airflow, louvres sized for free area rather than for the hole in the wall, and the controls that keep them working together.

For hazardous areas the fan and the controls change: explosion-proof motors, interlocked ventilation and gas detection. We build to the classification the integrator specifies, and the certification for the equipment stays with its supplier.

Where it is typically used

Equipment rooms with a heat loadCooling sized in kW against the design ambient, not in “horsepower” against the floor area.
Battery and process roomsVentilation interlocked to gas detection, with an ATEX fan where classified.
Dusty and coastal sitesFiltered intake, sealed penetrations and a unit rated for the corrosion class.
Cold climatesHeating, trace protection and a cold start to −40 °C.
02 / SPECIFICATIONS

Key specifications

Cooling capacity 3–25 kW per unit, with N+1 on request
Ambient range −40 °C to +55 °C, derating stated above 45 °C
Ingress IP55 for the unit, IP65 on request
Ventilation Axial or centrifugal fans, 500–20,000 m³/h, thermostatic or VFD control
Louvres Fixed, adjustable or motorised; free area stated as a percentage
Filtration G3 to F7 depending on the dust load, with a differential pressure gauge
Hazardous area ATEX / IECEx fans and controls to the classification you specify
Heating 1–6 kW with thermostat and frost protection
Control Thermostat, differential pressure alarm, fan failure alarm, dry contacts
Corrosion Coated coil and stainless fasteners to the enclosure class
Power 220 V single phase or 380–415 V three phase
Build time 10–20 days as a fitted system

Figures are for the standard configuration and change with the project. Values are design values; acceptance follows the contract technical agreement.

03 / WHAT IS INSIDE

What goes in the box

Installed, wired and tested before dispatch. On site the work is placement and external connections.

01Cooling unit

Split, wall-mount or roof-mount, sized to the loss figure at the design ambient.

02Ventilation

Fans and ducting sized from the required airflow, with a filter and a pressure gauge.

03Louvres

Free area calculated, not guessed; motorised where the room needs to close down.

04Heating

Thermostatic heaters and frost protection for cold sites.

05Controls

Thermostats, alarms and dry contacts to the site system, wired and tested.

06Penetrations

Sealed frames and gaskets so the air goes where it was designed to go.

04 / MODELS

Which model to take

Model Cooling Airflow Use
EQ-HVAC-5 5 kW 1,500 m³/h 10 ft room, battery or telecom
EQ-HVAC-10 10 kW 3,000 m³/h 20 ft equipment room
EQ-HVAC-25 25 kW 8,000 m³/h 40 ft room or process area
EQ-HVAC-EX 5–15 kW 3,000–6,000 m³/h Hazardous area, ATEX fan

Standard models are listed. Other capacities are built to order, with two to three weeks added to the standard lead time.

05 / TECHNICAL NOTES

Louvre free area is about half the hole, and that is where rooms go wrong

ENGINEERING NOTE

Free area, not opening size

A louvre with 50% free area passes half the air you would expect from its dimensions. Size a room on the opening and the fan runs against a pressure drop it cannot overcome, the airflow collapses and the room overheats with the fan running.

We state free area as a percentage on the schedule, and we size the fan from the system curve including the filter, which gets worse as it loads.

A sealed box cannot be cooled cheaply

If the enclosure must be IP65, the cooling has to reject through a coil with an external fan, not through a louvre. That is a different product and roughly twice the cost per kW — better to know at enquiry than at installation.

The same applies to hazardous areas: an ATEX fan and an interlocked control panel change the price more than the cooling unit does.

Free area, airflow and cooling capacity are stated on the schedule. If the equipment load changes, the whole air side is re-run rather than topped up.

06 / SELECTION

When to use it, when not to

These come from projects rather than general advice. Match your case against them; it is more useful than reading the specification table.

You have a heat loss figure in kW and a design ambient.

That is the whole calculation.

The room must stay sealed against dust or water.

We will quote a coil-based unit rather than a louvre.

The area is classified.

ATEX fans and interlocked controls, built to your classification.

The room is naturally ventilated and the load is under 2 kW.

Louvres and a fan will do; cooling would be wasted money.

You need comfort cooling for people.

A person needs fresh air, not just a cold room — a different design.

07 / DELIVERY

From contract to energisation

Data

Loss figure in kW, design ambient, ingress requirement, classification, power available.

Selection

Unit selection and air-side schedule in 3–5 days.

Contract

Order placed; long-lead ATEX items confirmed first.

Production

10–20 days as a fitted system, or supplied loose for your own fit-out.

Handover

Commissioning record, airflow measurement and alarm test.

08 / GALLERY

On site and in detail

Louvred ventilation panels on an equipment container
Louvred ventilation panels on an equipment container
Cooling unit and louvre detail on a container wall
Cooling unit and louvre detail on a container wall
Interior ventilation and drainage detail
Interior ventilation and drainage detail
Louvred door bank with filter frames
Louvred door bank with filter frames

Some images are scheme illustrations and renders showing structure and layout. Final delivery follows the contract drawings.

09 / FAQ

What customers ask most

Can you supply loose units for our own fit-out?

Yes — unit, louvres, filters and controls shipped as a kit with the schedule. Many integrators prefer it that way.

What is the lead time on ATEX fans?

Four to eight weeks depending on the certification route. It sets the schedule for the whole room, so raise it early.

Do you do the ducting?

For a container we do, in galvanised or stainless. Site ductwork is by others and we will review the drawing.

How often do filters need changing?

On a dusty site, monthly. That is why we fit a differential pressure gauge — it tells you when, instead of a date on a wall.

Can cooling be N+1?

Yes, on rooms above about 10 kW. Two units at part load also last longer than one at full load.

Ask for a scheme for your site

Send the capacity, rack count, site conditions and local climate. You get a layout, a single-line diagram and a price, at no charge, revised until it works.

See the enclosure range

Product Details
gallery
RELATED PRODUCT
Card Eq Skid
Skid Base & Lifting Frame — ISO Corners, Lifting Lugs, Sea-Fastened
Card Eq Shell
Custom Equipment Shell — Cuts, Doors, Coating and Insulation to Your Drawing
Card Eq Lab V2
Mobile Laboratory Container — Fume Extraction, Bench and a Sink That Drains
Telecom equipment shelter with louvre panels (catalogue crop)
Telecom & Edge Equipment Shelter — Walk-In, IP55, DC Powered
Contact us

Committed to providing customers with high-quality and reliable container solutions.