A row of water-cooled mining containers below a mountainside

Project case · Hydro-powered compute · Client confidential

Two point four megawatts on a river that never freezes

A hydro operator in the Caucasus spilled three megawatts of spring meltwater every year because the grid could not take it. We put the machines where the water was.

24containers
2.4 MWcompute load
45days to energise
1,900 msite elevation
ClientHydro generator (confidential)
LocationCaucasus, 1,900 m elevation
Scope24 × 40 ft water-cooled compute halls
ContractSupply, DDP and commissioning
Handover2025
01 / The brief

Spilled water is lost revenue, and the grid will not take it

What the client was up against

The plant runs on snowmelt with a pronounced spring peak. Through May and June the turbines can produce more than the regional grid will accept, and there is no storage behind the intake. The excess goes over the spillway.

The site is at 1,900 m, four hours from the nearest town on a road that closes to heavy vehicles in winter. Building anything conventional there meant a construction season, a crane, and a crew living on site.

What we proposed

Put the load at the plant instead of moving the power: 40 ft water-cooled containers fed directly from the penstock, using the same water twice — once through the turbines, then through the container heat exchangers before it returns to the river.

Water cooling is what makes the site work. Air-cooled halls at 1,900 m lose capacity in summer and need fan power that eats the margin; a closed water loop holds setpoint at any ambient and adds no acoustic load to a valley that has a village in it.

02 / What we delivered

Three systems, and the river does the heavy lifting

40 ft water-cooled container
01 / Compute40 ft water-cooled container

210 machines per hall on a closed loop, inlet held at 32 °C. Each hall has its own pump set, so one loop can be isolated without stopping the row.

Heat rejection skid
02 / WaterHeat rejection skid

Plate exchangers against the penstock flow: no chillers, no dry coolers, no evaporative loss. Rejected heat leaves with the water that was going downstream anyway.

Substation and paralleling
03 / PowerSubstation and paralleling

MV take-off from the plant switchyard, step-down and paralleling on a skid, with per-hall metering so hashrate can be matched to water flow hour by hour.

03 / Sequence

Forty-five days, and the road was the critical path

D0Flow dataTwelve months of turbine and spill records reviewed to size the load.
D12Design freezeLoop temperatures and pump heads agreed with the plant engineer.
D30Factory testFull-load wet test on the client’s water chemistry.
D38Up the valleyTwenty-four halls trucked in over six days between weather windows.
D45On the penstockLoops tied in, power closed, first hall hashing at 92% of nameplate.
04 / By the numbers

What the plant gained

2.4 MWof spring spill turned into revenue
0.031USD per kWh, the plant’s own cost of generation
45days from contract to first hall hashing
0chillers, dry coolers or evaporative water on site

Energy cost is the client’s internal generation cost, not a market tariff. Load, elevation and schedule are rounded. Client and river are not identified.

05 / Site record

Site record — the valley, the penstock, the halls

Halls on the bench below the intake while the pad works were still open
Halls on the bench below the intake while the pad works were still open
Water loop headers and fan wall at the end of a hall
Water loop headers and fan wall at the end of a hall
Machine rows: 210 per hall, cabled overhead
Machine rows: 210 per hall, cabled overhead
Halls staged at the plant yard before the road opened
Halls staged at the plant yard before the road opened
Figures & disclosure

Published as an anonymised reference. The client is not named and the site location is given only to region level. Commercial values (contract sum, unit price) are withheld; the technical figures describe the configuration as delivered. Where a number has been rounded or scaled for confidentiality it is stated in the note above.

What is your spill, and what does a kilowatt-hour cost you?

Send twelve months of generation and flow data. We will size the load to the water, not the other way round, and tell you what the loop has to be.

Talk to an engineer

Contact us

Committed to providing customers with high-quality and reliable container solutions.

ACTBOXES Whatsapp