ACTBOXES mining containers and a dry cooler on a pad in Dumas, Texas

Project case · Water-cooled compute · Dumas, Texas

Dumas, Texas: a water-cooled container hall beside a three-phase line

The containers arrived on a flatbed and the utility connection was still being made when they landed. That overlap is normal on rural sites, and it is the reason the electrical scope was separated from the cooling scope from the first drawing.

Watercooled, sealed loop
Dry cooleron the same pad
3-phaseoverhead service
2025on site
ClientCompute operator (not named)
LocationDumas, Texas, United States
Scope40 ft water-cooled compute containers, dry cooler, PDU, suppression
ContractFabrication, cooling loop, electrical fit-out, site support
SiteRural pad, overhead three-phase, dry climate, high dust
01 / The brief

Two trades, two schedules, one pad

Why water

Out here the air is dry and the dust is fine. An air-cooled hall pulls that dust through the condensers all summer and pays for it in cleaning labour. A sealed water loop with a dry cooler at the end keeps the machine room closed and puts the heat rejection where a hose can reach it.

The trade is plumbing. A water-cooled container is a machine with two fluid circuits, not a box with fans, and the commissioning is a pressure test before it is a power-up.

Why the overlap

A rural service is its own project. The pole, the transformer and the metering are the utility’s schedule, not ours, and on this site that work was still running when the containers arrived.

Keeping the two scopes separate meant the containers could be set, levelled and pressure-tested while the line crew finished, and the electricians could terminate into a container that was already proven.

02 / What we delivered

Three details that were decided on the pad

Landed, then levelled
01 / SetLanded, then levelled

Slings stay on until the unit is on its plinth and the levels are read. On a gravel pad, a container that looks level is rarely level.

A compartment you can work in
02 / TerminateA compartment you can work in

Terminations in a dedicated electrical compartment at the door end, not scattered along the wall. It is the difference between a two-hour job and a two-day job when something needs changing.

Dry cooler on the same pad
03 / Reject heatDry cooler on the same pad

The cooler sits beside the container it serves, on its own plinth, with the pipe run short and visible. Long buried runs are where water-cooled sites go wrong.

03 / Sequence

From flatbed to first hash

Step 1Pad and plinthsPlinths set to survey, drainage falls checked before delivery.
Step 2Land and levelCrane or boom lift per unit; slings released only after levels are read.
Step 3Loop and testWater circuit pressure-tested and flushed before any power is applied.
Step 4Power and terminateService, isolator, PDU and metering terminated per unit.
Step 5CommissionCooling, controls and failover proven with racks live.
04 / By the numbers

What was actually on the pad

Sealedwater loop, no site water
Drycooler on its own plinth
Per unitisolator and metering
Dustthe reason for the sealed room

Configuration as delivered. Unit count, load and commercial terms are not disclosed.

05 / Site record

Delivery week, in the order it happened

The line crew working the pole above the container row
The line crew working the pole above the container row
A unit on the hook, coming off the flatbed
A unit on the hook, coming off the flatbed
Trench and earthing between units, before backfill
Trench and earthing between units, before backfill
Racks in and cabled, aisle clear
Racks in and cabled, aisle clear
Container control panel, cooling status on screen
Container control panel, cooling status on screen
Figures & disclosure

Photographs are from the delivered project. The client is not named. Commercial values are withheld; the figures describe the configuration as shipped.

Send the service size, the water analysis and the summer ambient.

Water quality decides the loop materials; ambient decides the cooler. Give us those two and a photo of the pad and we will send a layout with the plumbing scope separated from the electrical one.