Shore power for berths 803–805, built in a container and wired on the quay
A port power utility needed high-voltage shore power at three berths, in a salt-spray environment, without building a substation on the quay. The answer was three containers, integrated and tested before they were lifted into place.
A substation that arrives on a lorry
What the berths needed
Shore power at a container berth is a grid connection in a hostile place: salt in the air, humidity all year, vibration from the quay, and no room for a conventional substation building next to the crane rail.
The utility also wanted the equipment to arrive already commissioned. Site work at a live berth is slow and expensive, and every hour of crane downtime costs more than the enclosure.
What we delivered
A containerised system with the high-voltage variable-frequency drive, transformer and distribution gear inside, wired and commissioned in the factory against the grid-side conditions the utility supplied.
The shell is heavy-duty coated for salt spray, with industrial air conditioning for thermal control, clean-agent fire suppression and remote monitoring. On site it is a lift, a cable termination and a commissioning check — not a construction project.
Three details that decide whether it lasts ten years

Heavy-duty coating system and sealed penetrations. Coastal corrosion is what ends these units early when the specification is left at a standard marine primer.

Industrial air conditioning holds the internal temperature and keeps salt-laden air out of the switchgear room. On a berth, louvres alone pull the sea inside.

Detection and clean-agent suppression inside the electrical compartment, interlocked with the ventilation and the door. No water on live gear.
From berth survey to energisation
What the installation actually has to hold
Values describe the configuration as delivered. Berth numbers are as published; commercial terms are not disclosed.
The units, at the berth and before it




The products this specification maps to
Published as an anonymised reference. The client is not named and the site location is given only to region level. Commercial values (contract sum, unit price) are withheld; the technical figures describe the configuration as delivered. Where a number has been rounded or scaled for confidentiality it is stated in the note above.