A row of air-cooled mining containers on a desert pad at dusk

Project case · Air-cooled compute farm · Client confidential

A compute farm that earns money when it switches off

Eighteen megawatts of interruptible load is an asset to a grid operator. This site was designed for the demand-response market first and hashrate second — which changed every decision from the cooling setpoint to the control system.

18 MWinterruptible load
40containers
4 hnotice to curtail
1.09PUE
ClientCompute operator (confidential)
LocationGulf region, desert site
Scope40 × 40 ft air-cooled halls, 18 MW
ContractSupply and commissioning, phases 1–3
Handover2025–2026
01 / The brief

Hashrate is volatile. Grid capacity payments are not.

What the client was up against

A single-revenue compute site is a bet on one number moving in one direction. The client wanted a second revenue line that does not care about the price of a coin: being paid to be available, and being paid more to stop.

Demand response is unforgiving about hardware. Curtailment in four hours means the whole plant has to come off load in a controlled way, without tripping the feeder, and come back without a restart queue that loses a day.

What we proposed

Design the plant around the curtailment signal. Every hall has its own contactor, its own meter and a defined ramp profile, so the site controller can drop from 18 MW to 2 MW in staged blocks and restore in the same order.

Air cooling rather than water because the site has no water and no wish to buy any. The penalty is a higher PUE and a capacity derate on the hottest afternoons — both of which are priced into the capacity contract and both of which were accepted at design stage.

02 / What we delivered

Three systems built for a curtailment signal

40HC air-cooled hall
01 / Compute40HC air-cooled hall

336 machines per hall, front-to-rear air, louvred end walls. Each hall is a single contactor block with a defined 90-second ramp down.

PDU and site controller
02 / ControlPDU and site controller

Per-position metering to the PDU, aggregated at the site controller. The curtailment logic sits in the controller, not in the machines, so it works with any firmware.

Detection and clean-agent suppression
03 / SafetyDetection and clean-agent suppression

Aspirating detection per hall with clean-agent suppression, isolated from the power path so a suppression event and a curtailment never collide.

03 / Sequence

Ninety days for phase one, then a repeatable block

D0Capacity studyFeeder headroom and curtailment windows agreed with the utility.
D15Hall designRamp profile, metering points and isolation per hall frozen.
D45Factory testRamp-down and ramp-up sequence rehearsed with the site controller.
D70Phase oneTwelve halls landed and energised; curtailment demonstrated to the utility.
D90Phases 2–3Remaining twenty-eight halls on the same controller, same profile.
04 / By the numbers

What the plant is paid for

18 MWof interruptible load registered with the utility
4 hnotice, with a 90-second ramp per hall
1.09PUE in winter, 1.31 at the July peak
40halls under one controller

Curtailment terms vary by market and are withheld. PUE values are design figures measured at the factory test, not annualised site averages.

05 / Site record

Site record

Phase one laid out at the staging yard, waiting on pad handover
Phase one laid out at the staging yard, waiting on pad handover
Halls staged before pad works finished
Halls staged before pad works finished
Side wall and service door; blanking panels on the louvre bank
Side wall and service door; blanking panels on the louvre bank
Machine rows inside a completed hall
Machine rows inside a completed hall
Figures & disclosure

Published as an anonymised reference. The client is not named and the site location is given only to region level. Commercial values (contract sum, unit price) are withheld; the technical figures describe the configuration as delivered. Where a number has been rounded or scaled for confidentiality it is stated in the note above.

Is curtailment part of your revenue, or just a risk?

Tell us the feeder limit and the notice period you have been offered. We will design the hall blocks, the ramp profile and the controller around it.