Rows of containerised data halls lit at night on a Texas site

Project case · Container data centre · Texas, United States

Thirteen halls on a Texas grid connection, four months from order

A technology company needed compute capacity next to a substation in West Texas, on a schedule the local construction market could not meet. Thirteen containerised halls, energised in four months.

13data halls
5.2 MWconnected load
4months to energise
40 ftper hall
ClientTechnology company (confidential)
LocationWest Texas, United States
Scope13 × 40 ft containerised data halls
ContractSupply, delivery and commissioning
Handover2024
01 / The brief

The substation was ready. The building was not.

What the client was up against

The site had a high-capacity connection and cheap power, and nothing else. Concrete, steel and mechanical trades in that part of Texas were booked out on data-centre work, and a shell-and-core package was quoting twelve to eighteen months before the first rack could be powered.

Compute demand does not wait for a construction market. Every month between the connection being available and the machines being installed was a month of paid-for power capacity with nothing drawing on it.

What we proposed

Thirteen 40 ft halls built as plant, not as a building: each one arrives with its racks, busway, cooling and power distribution installed and tested, and only needs a pad, a feeder and a network drop on site. The site work that remains is the part a local contractor can do quickly — pads, trenching, terminations.

Hall count was set by the feeder capacity rather than by a floorplate, so the thirteenth hall fits the same electrical room as the first. Adding capacity later means adding a container, not pouring a slab.

02 / What we delivered

Three systems, sized to the feeder rather than to a building

40 ft hall, air-cooled
01 / Compute hall40 ft hall, air-cooled

Rack rows on a raised grid, hot air ducted to louvred end walls. Sized for 400 kW per hall at 35 °C ambient, which is the design day in West Texas.

Substation and paralleling skid
02 / PowerSubstation and paralleling skid

MV interface, step-down and paralleling on a single skid outside the halls, so switchgear stays accessible without opening a compute space.

Dry cooler bank
03 / Heat rejectionDry cooler bank

Adiabatic-assisted dry coolers on a common header. Water use is limited to the handful of weeks a year when dry cooling alone cannot hold setpoint.

03 / Sequence

Four months, with the first hall live in ten weeks

W0OrderHall count and per-hall load fixed against the feeder capacity.
W3ShellsForty-foot shells welded, insulated and fitted with rack grids.
W6ElectricalBusway, PDU and paralleling gear installed and point-to-point checked.
W10First powerFirst four halls on site; feeder terminated; compute energised.
W17Full handoverThirteen halls online, cooling balanced, monitoring handed to the client NOC.
04 / By the numbers

What the site runs today

13halls, 40 ft each, on one feeder
5.2 MWconnected compute load
10weeks from order to first hall energised
400 kWper hall at 35 °C design ambient

Site location is given to state level and the client is not named. Load and schedule figures are rounded; the per-hall rating is the delivered design value.

05 / Site record

Site record

The hall rows from above: cooling compound to the north, feeder to the west
The hall rows from above: cooling compound to the north, feeder to the west
Three halls on line, dry coolers running at dusk
Three halls on line, dry coolers running at dusk
Hall front: louvred end wall, service door, metering at the corner
Hall front: louvred end wall, service door, metering at the corner
Rack rows inside before the customer equipment was installed
Rack rows inside before the customer equipment was installed
Figures & disclosure

Site, scale and dates are as published for this project. Commercial values are withheld. Technical figures describe the configuration as delivered; the note above states which values are rounded.

How much load, how fast, and what does the feeder allow?

Send the feeder capacity and the site plan. We will come back with a hall count, a power single-line and a shipping schedule that fits the connection date.

Talk to an engineer

Contact us

Committed to providing customers with high-quality and reliable container solutions.

ACTBOXES Whatsapp