Aerial view of a modular data centre campus with white IT halls

Project case · Modular data centre · Client confidential

Twelve IT halls, live in ninety days

A colocation operator had the land, the anchor tenant and the power application. What it did not have was eighteen months for a permanent building. We shipped the building instead.

12IT halls
4.8 MWIT load
90days to handover
2,100 m²white space
ClientColocation operator (confidential)
LocationSoutheast Asia
Scope12 IT halls, power, cooling, fire suppression
ContractDesign-build, DDP to site
HandoverQ3 2026
01 / The brief

The grid connection was eighteen months out. The tenant was not.

What the client was up against

The site was a cleared industrial plot with a medium-voltage connection applied for but not energised, and a planning consent that covered an equipment yard rather than a permanent building. The anchor tenant had signed for the first four halls on a date certain.

A conventional build — slab, steel frame, envelope, fit-out — ran eighteen to twenty-four months from consent to first rack. That put the tenant’s start date outside the contract, and put the operator’s revenue behind the whole programme.

What we proposed

Build the hall as a product, not as a construction project: factory-finished 40 ft halls with the racks, containment, UPS and cooling already inside, delivered DDP and set on pads. Groundworks, cabling and the utility interface stay on site; everything else leaves the factory complete and tested.

The trade is density for speed. A prefabricated hall carries less weight per square metre than a purpose-built shell and it will not take a fourth floor. For a phased colocation campus that was never the constraint — time to first revenue was.

02 / What we delivered

Three systems, one shell — and each one arrives tested

40 ft data hall
01 / IT hall40 ft data hall

24 rack positions at 8 kW average, hot-aisle contained, dual A/B busway overhead. The hall leaves the factory pressure-tested with the racks fitted.

2N UPS and N+1 generation
02 / Power2N UPS and N+1 generation

Two 400 kW UPS lines per hall, one shared N+1 generator set behind an automatic transfer scheme. Battery autonomy sized to generator start plus ten minutes.

Chilled water with dry coolers
03 / CoolingChilled water with dry coolers

Row-based chilled-water units with an outdoor dry cooler bank. Free cooling for roughly 4,000 hours a year at this latitude, PUE 1.35 at 60% load.

03 / Sequence

Ninety days, five gates — and the date was fixed at contract

D0Design freezeSingle-line, layout and load schedule signed off in one week.
D10Steel and panelsShells cut, welded and insulated; racks and busway staged.
D45Factory testPower-on, cooling and controls witnessed before the container closes.
D62On siteTwelve halls landed over four nights, set on pads, bolted and sealed.
D90EnergisedUtility interface closed, halls commissioned, first tenant rack live.
04 / By the numbers

What the operator actually got

12halls, 2,100 m² of white space
4.8 MWIT load connected, 2N on the UPS path
90days from contract to first energised tenant rack
1.35design PUE at 60% load, free cooling for 4,000 hours a year

Figures are the as-built values from the commissioning report. Some details are rounded to protect the client’s identity.

05 / Site record

Site record — groundworks to first power

Phase one complete: twelve halls, dry cooler yard, MV compound
Phase one complete: twelve halls, dry cooler yard, MV compound
Three halls after energisation, dry coolers running
Three halls after energisation, dry coolers running
A hall on its pad before the cable entries are dressed
A hall on its pad before the cable entries are dressed
Inside the shell before the racks go in
Inside the shell before the racks go in
Figures & disclosure

Published as an anonymised reference. The client is not named and the site location is given only to region level. Commercial values (contract sum, unit price) are withheld; the technical figures describe the configuration as delivered. Where a number has been rounded or scaled for confidentiality it is stated in the note above.

Tell us the load, the site and the date. We will tell you what fits.

Send a single-line diagram and a site plan, and we will come back with a layout, a shipping plan and a delivery date — not a brochure.

Talk to an engineer

Contact us

Committed to providing customers with high-quality and reliable container solutions.

ACTBOXES Whatsapp