White equipment containers lined up on a concrete apron before dispatch

Project case · Energy storage · Factory integration

The battery cabin is finished and tested before it reaches the site

A storage integrator moved commissioning indoors: racks, BMS, distribution, thermal management and suppression installed and cycle-tested at the factory, so the site work is a foundation and a cable.

Full stringracks and BMS installed
Cycle testedbefore dispatch
One liftonto a prepared foundation
Daysof site work, not weeks
ClientStorage system integrator (confidential)
LocationSouthern China
ScopeBattery cabin integration and factory commissioning
ContractEnclosure supply, integration, test, delivery
TestCharge and discharge cycles with the BMS and thermal system live
01 / The brief

Commissioning is the part that ruins the schedule

The problem with site commissioning

A battery cabin contains racks, a battery management system, DC distribution, thermal equipment and suppression. Put all of that together on site and you have a commissioning task measured in weeks, in weather, with the racks already in place and no easy way to reach behind them.

It also splits responsibility. When something does not balance, the enclosure supplier, the rack supplier and the integrator each have a plausible explanation, and the project stops while they work out whose it is.

What we changed

The cabin is integrated at the factory: racks set out, busbars run, BMS wired, thermal and suppression installed, then the whole string is cycled with the controls live and the results recorded against a test sheet.

On site the unit arrives complete. The scope is a foundation, a lift, a cable termination and a repeat of the functional checks. Everything that could go wrong in a way that costs a week has already gone wrong in a shed where it costs a day.

02 / What we delivered

What gets closed out before the doors shut

Set out and torqued to a drawing
01 / RacksSet out and torqued to a drawing

Rack positions, busbar torque and clearances checked against the layout, with the record filed per cabin rather than per project.

BMS talking to everything
02 / ControlsBMS talking to everything

BMS, thermal controller and suppression panel integrated and addressed before the cycle test, so the test exercises the real control path.

Cooling proven under load
03 / ThermalCooling proven under load

Thermal performance demonstrated during charge and discharge, not assumed from a datasheet. The cabin is accepted at temperature.

03 / Sequence

From rack delivery to site handover

Step 1LayoutRack positions, cable routes and service clearances fixed on a drawing.
Step 2AssemblyRacks, busbars, BMS, thermal and suppression installed.
Step 3Cycle testCharge and discharge run with the real control path live.
Step 4DispatchCabin sealed, shipped with its test record and as-built drawings.
Step 5SiteFoundation, lift, cable termination, functional checks repeated.
04 / By the numbers

What moves from the site to the factory

Racks and BMSinstalled and addressed in the factory
Cycle testrun before dispatch, results recorded
One liftthe only heavy operation on site
Daysof site work instead of weeks

Values describe the configuration as delivered. Cabin count and commercial terms are not disclosed.

05 / Site record

Integration, then dispatch

Sister build: a walk-in enclosure interior, lined and lit before the equipment goes in
Sister build: a walk-in enclosure interior, lined and lit before the equipment goes in
Sister build: a completed storage cabin on the test apron
Sister build: a completed storage cabin on the test apron
Cabin lifted complete, systems already installed
Cabin lifted complete, systems already installed
Cable penetrations and panel gear inside the cabin
Cable penetrations and panel gear inside the cabin
Figures & disclosure

Published as an anonymised reference. The client is not named and the site location is given only to region level. Commercial values (contract sum, unit price) are withheld; the technical figures describe the configuration as delivered. Where a number has been rounded or scaled for confidentiality it is stated in the note above.

Send the rack schedule and the site date.

Tell us the string size, the thermal duty and when the foundation will be ready. We will come back with an integration scope and a factory test plan.

Talk to an engineer

Contact us

Committed to providing customers with high-quality and reliable container solutions.

ACTBOXES Whatsapp