Three two-storey blocks built from six red 40 ft containers on a bare site

Project case · Custom container build · Two-storey block

Six 40 ft containers, two storeys, one afternoon of crane time

Three blocks, two boxes each, on bare earth. The upper floor is almost all glass, held in place by bracing that was left visible on purpose. The lower floor is open behind sliding doors. Everything was cut and welded before it left the workshop.

640 ft containers
2 storeysthree linked blocks
6 mglazed opening per bay
1 daycrane on site
ClientPrivate developer (not named)
LocationChina, site not disclosed
Scope6 × 40 ft containers in three two-storey blocks, full-height glazing
ContractStructural design, cutting and reinforcement, glazing, delivery and crane placement
SiteBare earth, no slab, 12 m trailer access from the lane
01 / The brief

What happens when you cut six metres out of a wall

The side wall was holding the box square

A 40 ft side wall is the shear panel. Take six metres out of it for glass and you have replaced a wall with one beam, two posts and a promise. The box will still stand, but it will rack: the diagonals change length, the doors stop lining up, and the glazing takes the movement until something cracks.

So the opening gets a frame before the glass gets an order. Top beam, bottom beam, a post at each end, welded into the corner posts. On the upper floors we left the cross bracing on the outside face and painted it the same red. It was doing structural work anyway; hiding it would have cost more than showing it.

The top box sits on the bottom box

There is no steel frame between the floors. The upper container lands directly on the four corner castings of the lower one. That only works if the lower box is dead level: five millimetres out at the bottom becomes ten at the top, and the joint reads as a mistake from thirty metres away.

The ground here is earth, not concrete. Twelve pads, a level, and a torque wrench did the job a slab would have done, at a fraction of the cost. The pads also keep the steel out of the water that collects after rain.

02 / What we delivered

Three details that decide whether it reads as a building

Glass goes in last
01 / OpeningGlass goes in last

Cut, weld, grind, paint, then glaze. Welding spatter on a finished pane is a scar you cannot polish out, and replacing one means taking the frame apart. The order of operations is the whole job.

The X stays outside
02 / BracingThe X stays outside

Diagonal bracing on the facade, painted body colour. Clients usually ask for it hidden behind a ceiling. Here it became part of the elevation, which is cheaper and honest about how the box stays square.

Corner casting on corner casting
03 / StackingCorner casting on corner casting

No spreader frame between the floors. Four points, checked with a level, then welded. Slings go through the castings, never around the wall panels — a 1.2 mm sheet will fold before it lifts anything.

03 / Sequence

Five steps, one yard

Step 1Set the padsTwelve pads, levelled to 5 mm, before the first trailer arrives.
Step 2Land the ground floorTwo boxes per trip, three trips. The trailer reverses to the lift point.
Step 3StackUpper box onto lower castings. Crane stops if wind passes 8 m/s.
Step 4GlazePanels measured after the frames are welded, not before. Glass arrives last.
Step 5Roof and edgesParapet, gutter, downpipes. Two coats of sealant on every joint.
04 / By the numbers

The build, in four numbers

640 ft containers
2storeys, three linked blocks
12.19 mlength of each shell
5 mmtolerance at the castings

Dimensions from the container plates and site measurement. Commercial values are not disclosed.

05 / Site record

The site, in the order it happened

A box coming through the gate on a trailer, still on its original paint
A box coming through the gate on a trailer, still on its original paint
The upper box on the hook, slings through the castings, coming down onto the first floor
The upper box on the hook, slings through the castings, coming down onto the first floor
From the roof next door: the blocks against the hills, one facade still unwrapped
From the roof next door: the blocks against the hills, one facade still unwrapped
Figures & disclosure

Photographs are from the delivered project. The client is not named and the site is not disclosed. Commercial values are withheld; the figures describe the build as shipped.

Tell us the opening, not the drawing.

How wide the glass runs, which floor it sits on and what the ground is made of decide the frame, the bracing and the lifting plan. Send those three and we can price the shell before anyone draws an elevation.